The following information applies to the period of Dec. 12-18:
The following is expected as a result of a project to complete a new north-south water transmission line on the eastside of Carson City.
• There will be a lane closure with flagger-controlled traffic on Fairview Drive south of Fifth Street.
• Fifth Street will be closed between Fairview Drive roundabout and Butti Way from 9 p.m. to 6 a.m. Detours will be marked.
There will be work at the following locations as a result of the Freeway Landscaping Project. No closures are expected.
• North Carson Street, in the vicinity of the freeway overpass.
• Arrowhead Drive between North Carson Street and Garnet Way.
• Northgate Lane between Jumbo Court and Dyer Court.
• Emerson Drive between Mark Way and College Parkway.
• East College Parkway, in the vicinity of the freeway overpass.
There will be work off-street due to the installation of gateway signs at the following locations. There will not be any lane closures, but use caution:
• The north shoulder of Highway 50 East between Arrowhead Drive and Flint Road.
• The east shoulder of Highway 395 just north of Topsy Lane.
• Near the southbound Carson City Freeway off-ramp at North Carson Street.
The following activity is expected due to utility work.
• On Monday and Tuesday, there will be flagger-controlled traffic on Emerson Drive just south of Arrowhead Drive. Minor delays are expected.
• On Tuesday, there will be a lane closure with flagger-controlled traffic on Garnet Way just north of Arrowhead Drive.
For information, call Patrick Pittenger at 887-2355 Ext. 7396.
Comments
Use the comment form below to begin a discussion about this content.
Sign in to comment