Road report as of Thursday. The following applies to Dec. 5-11:
Road closures are expected at the following locations due to road/utility work:
Caroline Street between Valley Street and Anderson Street will be closed, Monday-Thursday, 7 a.m. to 5:30 p.m. for roadway reconstruction.
Musser Street between Plaza Street and Stewart Street will be closed, Monday and Thursday, 7 a.m. to 5:30 p.m. for roadway reconstruction.
Northridge Drive between Table Rock Drive and Wilma Way will be closed in the westbound direction, Monday-Friday, 7 a.m. to 4 p.m. for utility work.
The following street segments will be closed for a special event, Saturday-Sunday, 5 to 8 p.m.:
Division Street between Telegraph Street and King Street
King Street (in the eastbound direction) between Minnesota Street and Division Street Minnesota Street between King Street and Telegraph Street
Musser Street between Phillips Street and Nevada Street
Proctor Street between Minnesota Street and Nevada Street
Lane restrictions are expected at the following locations due to road/utility work:
U.S. 50 between Russell Way and Airport Road will have lane and shoulder closures in the eastbound direction, Monday-Friday, 7 p.m. to 6 a.m. for roadway and sidewalk reconstruction. Work zone speed limits will be reduced to 35 mph, and drivers should expect minor delays. Pedestrians must use existing crosswalks to detour to the north side of the street.
The following streets will have narrowed lanes and shoulder work between Nevada Street and Mountain Street, Monday-Thursday, 7 a.m. to 5:30 p.m.: Caroline Street, Robinson Street, Spear Street and Telegraph Street.
Anderson Street between Washington Street and Robinson Street will have narrowed lanes, Monday-Thursday, 7 a.m. to 5:30 p.m. for roadway reconstruction.
Curry Street between 5th Street and Musser Street will have narrowed lanes, Monday-Thursday, 7 a.m. to 5:30 p.m. for roadway improvements.
Dori Street between Sherman Lane and Catherine Circle will be reduced to one lane with flaggers, Monday-Friday, 6 a.m. to 4 p.m. for utility work.
5th Street between Saliman Road and Warm Springs Road will be reduced to one lane with flaggers, Monday-Friday, 7 a.m. to 6 p.m. for utility work.
Hamilton Avenue between Bullion Drive and Belmont Avenue will have shoulder work, Monday-Friday, 9 a.m. to 5 p.m. for utility work.
Musser Street between Plaza Street and Stewart Street will have narrowed lanes, Tuesday-Wednesday, 7 a.m. to 5:30 p.m. for roadway reconstruction.
Northridge Drive between Roop Street and Ridgecrest Drive will have narrowed lanes, Monday-Friday, 7 a.m. to 4 p.m. for utility work.
Sheep Drive between Deer Run Road and Asphalt Drive will be reduced to one lane with flaggers, Monday-Friday, 7 a.m. to 4 p.m. for utility work.
Stewart Street between Telegraph Street and Musser Street will have lane reductions, Monday-Thursday, 7 a.m. to 5:30 p.m. for roadway reconstruction.