Carson City road report for February 28 to March 6, 2022


Share this: Email | Facebook | X
Road report as of Thursday. The following applies to Feb. 28-March 6:
Road closures are expected at the following locations due to road/utility work:
Robinson Street will be closed for sewer and water line replacement between 7 a.m. and 5:30 p.m. at the following intersections on the respective days: Monday at Elizabeth Street; Tuesday at Mountain Street; Wednesday at Division Street; Thursday at Minnesota Street.
Lane restrictions are expected at the following locations due to road/utility work:
Carson Street between Hot Springs Road and Winnie Lane will have shoulder work, Monday-Tuesday, 7 a.m. to 4 p.m. for utility work.
Curry Street between 5th Street and Musser Street will have shoulder closures and lane shifts, Monday-Friday, 7 a.m. to 5:30 p.m. for roadway reconstruction.
Edmonds Drive between Reeves Street and Brown Street will have shoulder work, Monday-Friday, 7 a.m. to 4 p.m. for utility work.
Long Street between Roop Street and Rand Street will be reduced to one lane with flaggers, Monday-Thursday, 7 a.m. to 5:30 p.m. for roadway reconstruction. Expect delays.
U.S. 50 between Lompa Lane and Airport Road will have sidewalk closures on the south side of the street. Follow detour signage.