BEFORE THE PUBLIC UTILITIES COMMISSION OF NEVADA
NOTICE OF SUPPLEMENT TO THE JOINT APPLICATION
On March 28, 2022, Nevada Power Company d/b/a NV Energy
(“NPC”) and Sierra Pacific Power Company d/b/a NV Energy (“SPPC”)
(collectively, “NV Energy”) filed with the Public Utilities Commission
of Nevada (“Commission”) a joint application, designated as Docket
No. 22-03028 (“Joint Application”), for approval to merge into a single
corporate entity, to transfer Certificates of Public Convenience and
Necessity (“CPC”) 685 Sub 20, 688, and 688 Sub 6 from SPPC to NPC,
and to consolidate generation assets.
On September 7, 2022, NV Energy and a majority of the parties
participating in this docket submitted a stipulation agreeing to vacate
the existing procedural schedule in order for NV Energy to address
concerns raised by the Regulatory Operations Staff of the Commission,
the Bureau of Consumer Protection, and other intervening parties. That
same day, the Commission issued Procedural Order No. 3, vacating the
procedural schedule.
On November 09, 2022, the Commission issued Procedural Order
No. 4 directing NV Energy to file supplemental direct testimony no later
than December 30, 2022.
On December 30, 2022, NV Energy filed a supplement to its Joint
Application (the “Supplement”), addressing several concerns previously
raised by parties participating in this docket.
This Notice serves only to notify the public that the Commission
has received the above-referenced filing. It is the responsibility of
interested persons to review the filing and monitor the proceedings to
determine their desired levels of involvement based on how this matter
may affect their unique situations. The details provided within this
Notice are for informational purposes only and are not meant to be an
all-inclusive overview of the filing. The Commission may consider and
adopt alternative proposals not contained within the filing, but which are
related to the subject matter of the filing and supported by substantial
evidence.
NV Energy filed the Joint Application and the Supplement pursuant
to the Nevada Revised Statutes (“NRS”) and the Nevada Administrative
Code (“NAC”), Chapters 703 and 704, including, but not limited to NRS
704.329, NAC 704.79971 through 704.79991, NRS 704.410, NRS
704.7565 through 704.7595, and NAC 703.535. Pursuant to NRS
703.190 and NAC 703.527 et seq., NV Energy requests that certain
information in the Joint Application receive confidential treatment.
In the Joint Application, NV Energy seeks approval to merge SPPC
into NPC, creating one legal entity while maintaining separate rate
jurisdictions. NV Energy also seeks authorization to transfer SPPC’s
electric CPC (No. 685 Sub 20), liquid petroleum gas CPC (No. 688),
and gas CPC (No. 688 Sub 6) to NPC, and to modify the transferred
CPCs to reflect the name of the surviving company: NPC. Additionally,
NV Energy seeks authority to transfer all of SPPC’s electric generation
assets to NPC, where they will continue to be used to provide utility
service to customers of NV Energy. The Supplement does not alter the
relief sought in the Joint Application but provides additional information
and clarification on how the merged utility will conduct its operations in
Nevada.
Interested and affected persons may file comments or petitions
for leave to intervene pursuant to NAC 703.578 through 703.600
electronically through the Electronic Filing System on the Commission’s
website or at either of the Commission’s offices on or before
WEDNESDAY, JANUARY 18, 2023. Parties already granted authority
to participate in this docket will retain their status in this docket with no
further action required.
A person who wishes to participate as a commenter may file written
comments pursuant to NAC 703.491. A commenter is not a party of
record and shall not take any action that only a party of record may
take. Pursuant to NAC 703.500, only parties of record are entitled to
enter an appearance, introduce relevant evidence, examine and crossexamine
witnesses, make arguments, make and argue motions and
generally participate in the proceeding.
The Joint Application and the Supplement are available for public
viewing at the Commission’s website: https://puc.nv.gov; and at the
offices of the Commission: 1150 East William Street, Carson City,
Nevada 89701 and 9075 West Diablo Drive, Suite 250, Las Vegas,
Nevada 89148.
A person must request in writing to be placed on the service list for
this proceeding to receive any further notices in this matter.
By the Commission,
__/s/______________________
TRISHA OSBORNE,
Assistant Commission Secretary
DATED: Carson City, Nevada
01/04/23
(SEAL)
Pub Date: January 11, 2023