Road closures are expected at the following locations due to road/utility work:

2nd Street between Carson Street and Curry Street will be closed to westbound traffic to June 30 for construction.

Center Drive between Alder Street and Clearview Drive will be closed to through traffic Monday-Friday, 7 a.m. to 5:30 p.m.

Gentry Lane between Snyder Avenue and Hudson Drive will be closed to through traffic Monday-Thursday, 7 a.m. to 5:30 p.m.

Lane restrictions are expected at the following locations due to road/utility work:

10th Street between Minnesota Street and Curry Street will be reduced to a single lane to March 21, 7 a.m. to 5 p.m.

The Carson Street and Koontz Lane intersection will have reduced lanes Monday, 1 a.m. to 3 a.m.

Clearview Drive between Silver Sage Drive and Center Drive will be reduced to a single lane Monday-Friday, 7 a.m. to 5 p.m.

College Parkway between the 395 Off Ramp and Research Way will have shoulder work Monday, 7 a.m. to 3 p.m.

Curry Street between Rhodes Street and 10th Street will be reduced to a single lane to March 21, 7 a.m. to 5 p.m.

Lompa Lane will have traffic shifts between College Parkway and Northridge Drive, Monday-Friday, 7 a.m. to 5:30 p.m.

Silver Sage Drive between Eagle Station Lane and Clearview Drive will be reduced to a single lane Monday-Friday, 7 a.m. to 5 p.m.