Road report as of April 22. The following applies to April 26-May 2:
Road closures are expected at the following locations due to road/utility work:
• Oak Street will be closed between Willow Street and Snyder Avenue, Monday-Wednesday, 7 a.m. to 5 p.m. for underground utility installation. Detours will be provided on Willow Street. Please use caution.
• Willow Street may be closed between Snyder Avenue and Oak Street beginning Tuesday as well as Wednesday-Thursday, 7 a.m. to 5 p.m. for underground utility installation.
• Snyder Avenue in the westbound direction will be closed between Carson Street and Oak Street, Thursday, 7 a.m. to 5 p.m. for underground utility installation. Eastbound traffic will be allowed, but westbound traffic will be detours to Clearview Drive
• Lane restrictions are expected at the following locations due to road/utility work:
Arrowhead Drive will have shoulder work between Convair Drive and Hytech Drive, Wednesday, 8 a.m. to 6 p.m. for utility boring. Please use caution when passing bicycles.
• U.S. 50 at Airport Road will have shoulder closures, Tuesday, 7 a.m. to 5:30 p.m. for manhole and utility work.
• Saliman Road will have lane closures and lane shifts in both directions between 5th Street and Robinson Street, Monday-Friday, 7 a.m. to 6 p.m. for utility installation associated with nearby development.
There may be periodic, overnight lane closures on South Carson Street between Fairview Drive and Clearview Drive as crews install signal equipment.